APPLICATION OF EFFECTIVE DISPUTES RESOLUTION IN CONSTRUCTION CONTRACTS IN RWANDA

Authors

  • OSIRI Jean D’amour Jomo Kenyatta University of Agriculture and Technology (JKUAT)
  • Prof. Stephen Diang’a School of Architecture Jomo Kenyatta University of Agriculture and Technology (JKUAT)
  • Dr. Titus Kivaa Jomo Kenyatta University of Agriculture and Technology (JKUAT)
Abstract views: 253
PDF downloads: 275

Keywords:

Application, effective Dispute resolution, construction contract.

Abstract

Purpose: As a vibrant and booming industry, the Rwanda construction industry has numerous contractual disputes that arise between different parties as projects advance with time. It is because of this that a third party will often be agreed upon by the employer and the contractor to resolve any issues or disputes that may arise. Rwanda Construction projects are becoming increasingly complex and as a result more complex contract documents are made, this in turn results in more challenging claims and disputes. Many forms of construction contracts are used in Rwanda such as FIDIC forms of contracts, World Bank, Rwanda Public Procurement Authority (RPPA) and other private forms of contracts. The aim of this study is to examine contract dispute resolution process and develop an effective approach for Rwanda.

Methodology: The approach of this study is both qualitative and quantitative as the research wants to focus on the application of effective disputes resolution in construction contracts in Rwanda especially in Kigali city.

Findings: At the first stage of construction contract preparation, every Construction project is expected to be performing as it is prepared within given time limit, estimated budget, detailed and with compliance to the client requirements. However undesirable project performance results have been reported from one project to another in various forms such as low productivity, delays, cost overrun, and poor quality as a result of variation.

Unique Contribution to Theory, Practice and Policy: Compliance with external political strategy and organization strategies was the main criteria in needs identification. There were change orders in a majority of the projects arising from change in needs during construction works. The contract development process was inefficient in many projects and led to inaccurate estimates that later negatively affected project performance.

Downloads

Download data is not yet available.

Author Biographies

OSIRI Jean D’amour, Jomo Kenyatta University of Agriculture and Technology (JKUAT)

Post Graduate Student

Prof. Stephen Diang’a, School of Architecture Jomo Kenyatta University of Agriculture and Technology (JKUAT)

Dean

Dr. Titus Kivaa, Jomo Kenyatta University of Agriculture and Technology (JKUAT)

Lecturer

References

Al., B. A. (2006). Assessing the effect on flood frequency of land use change via hydrology simulation. Journal of Hydrology, 324, 141-153.
Bramble, B. B. (1995). Resolution of Disputes to avoid construction claims. Washington : National Academy Press.
Burge, R. (1995). Guidelines and Principles for Social Impact Assessment. In Environ Impact Assess (pp. 11-45).
Ceric, A. (2003). framework for process-driven risk management in construction a. Uk:University of Salford.
Chaitanya Khekale, N. F. (2013). Management of Claims and Disputes in Construction. International Journal of Science and Research (IJSR), 1-1.
Chapman, P. (2006, November 30). Dispute Boards for Major Infrastructure Projects. Paper presented at seminar at the use of Dispute Boards in Australia.
Charrett, D. D. (2005). Special topic adjudication and dispute boards. The next wave in ADR.
charter, C. (2011). Rwanda Public Procurement Authority. kigali.
Clough, S. &. (2005). Construction Contracting: A Practical (7 ed.). london:Wiley.
Derrick, G. (2016, April 30 ). Different methods of dispute resolution in construction disputes.
Fenwick, E. (2000, May). The Arbitrator and mediator, V27, 57,58.
Fenwick, E. (2004, September 9). Nicholas Gould. Dispute Resolution in the construction industry.
J., B. (2002). Can ISO 14000 and eco-labelling turn the construction industry green? . In building and environment (pp. 421-428).
Khekale., C. (2013). Management of Claims and Disputes in Construction. InternationaJournal of Science and Research (IJSR).
MINICOFIN. (2014).
Muturi, C. &. (2014). Factors affecting adherence to cost estimates: A. International journal of social sciences and entrepreneurship, 1, 689-705.
Peter Love, P. D. (2007). Dispute Avoidance and Resolution.
planning, M. O. (2014).
Statement, S. D. (2016, 12 08). Retrieved from EB-ICS-DL@state.gov: https://www.export.gov/article?id=Rwanda-Dispute-Settlement
Tarar, M. (2011). Causes of Disputes in construction industry. Engineers Daily, 3.
Zhou, Z. (2007). Understanding the Key Risks in Construction (Vol. 25).

Downloads

Published

2019-05-15

How to Cite

Jean D’amour, O., Diang’a, P. S., & Kivaa, D. T. (2019). APPLICATION OF EFFECTIVE DISPUTES RESOLUTION IN CONSTRUCTION CONTRACTS IN RWANDA. International Journal of Entrepreneurship and Project Management, 4(2), 1 – 13. Retrieved from https://www.iprjb.org/journals/index.php/IJEPM/article/view/881

Issue

Section

Articles